On the evening of May 31, Minks 2 Project No.1 gas turbine generator combined to the grid at 19:22 (Minsk time), after debugging for nearly 5 hours. With the two sets of 32.5 MW gas turbine generation units of CCOEC’s Mink 2 project both passing the generation test smoothly, the technicians will hence make all efforts in preparing for the 72 hour-commissioning of the generation units, in the purpose of a smooth turning over of the project as soon as possible.