At 15:00 on February 13, 2012 Beijing time (10:00 on February 13, Belarus time), the 72-hour full load trial run was successfully carried out for the 1*399.6MW gas-turbine combine cycle generation unit of CCOEC’s Minsk 5 Thermal Power Plant Rehabilitation project. This marks another major achievement in the construction of the project, which is of great significance to the promotion of China-Belarus economic and trade cooperation and the economic development of Belarus.
Since the project was initiated for construction, with the support of CCOEC leaders as well as relevant department of the State Development Bank, the staff of Minsk 5 project spared no effort in promoting the project with scientific management, strict standard requirements and innovations, winning strong recognition from the proprietors of the project, who expressed congratulations to the successful completion of the 72-hour full load trial run.
We will set the success of the 72 hour trial run as a new start, strive hard to ensure the completion of the follow-up unit performance test with high quality and efficiency, making Minsk 5 a project of excellence and contributing to the economic and trade development of China and Belarus.